Farmington Meeting House
Stabilization and Relocation Project 2009-2010 Draft Budget

August 26, 2009

Phase 1: Stabilize, Weatherproof, and Shore for “Storage” on Site: $137,500

Phase 1A: Build a Pier and Slab Foundation at the New Location: $20,500

Phase 2: Shore for Movement. Relocate Building: 112,500

Contingency (10%): $27,000
Construction costs

Architect’s Fee (14%): $41,500
Design = 70%, Bidding = 5%, and Const. Admin. = 25%

Total Budget: $339,000